In 2022, the “ice altar” project of the comprehensive training center of the Winter Sports Management Center of the State General Administration of Sports, one of the training venues for the Beijing Winter Olympic Games, completed the pouring of the cold water jug training ice rink, this also marks the completion of the ice rink pouring in the project.
Xinhua News Agency, Beijing, May 7 (Reporter Luo Xin) the reporter learned from the third Construction Engineering Co., Ltd. of the second construction bureau on the 7th that, in 2022, the “ice altar” project of the comprehensive training center of the Winter Sports Management Center of the State General Administration of Sports, one of the training venues for the Beijing Winter Olympic Games, completed the pouring of the cold water jug training ice rink, this also marks the completion of the ice rink pouring in the project.
According to the introduction, the total construction area of “ice altar” is 33200 square meters, and the height of the main building is 30.15 meters. The project has 6 floors above the ground, 1 floor below the ground and 2 floors below the ground, including two ice rinses that meet the standards of international competitions. One of the ice rinses is the standard cold water jug training ground, the three-layer ice rink is a short track speed skating training site. One to three layers of de-icing off-site also includes scientific research and teaching rooms, medical rehabilitation rooms, restaurants, athlete lounges and other ancillary facilities; Four to six layers are athletes’ dormitories. On May 4, the concrete pouring of the first ice rink-short track speed skating rink was completed.
Under the premise of strictly controlling epidemic prevention, the “ice altar” project organized the resumption of work and production in an orderly manner. At present, there are more than 250 workers on site, mainly for ice rink construction and final interior decoration. It is expected that by the end of May, the “ice altar” project will complete all construction procedures.
According to the introduction, the comprehensive training hall of Winter Sports Management Center of the State General Administration of Sports is located in the South Street of Zhongguancun, Beijing, looking down from high altitude like a cross section of cold water jug, from the side, its facade is like “ice marks” after the end of short track speed skating, so it has the nickname of “ice altar. After the Beijing Winter Olympics, the “Ice Arena” will not only continue to be used as a training venue for the national team, but also as a place for national fitness and popularization of ice sports.